NOTICE OF 30‑DAY PERIOD
FOR PUBLIC COMMENT
Preliminary Findings Regarding the Renewal of a
Federally Enforceable State Operating Permit (FESOP)
for Jayco, Inc. - Topeka in LaGrange County
Permit No. 087-30645-00007
The Indiana Department of Environmental Management (IDEM) has received an application from Jayco, Inc. - Topeka located at536 Michigan Street, Topeka, Indiana for a renewalof their FESOP issued on March 22, 2007. If approved by IDEM’s Office of Air Quality (OAQ),this proposed renewalwould allow Jayco, Inc. - Topeka to continue to operate their existing source.
This draft FESOP does not contain any newequipment that would emit air pollutants; however, some conditions from previously issued permits/approvals have been corrected, changed or removed. These corrections, changes and removals may include Title I changes. This notice fulfills the public notice procedures to which those conditions are subject. IDEM has reviewed this application, and has developed preliminary findings, consisting of a draft permit and several supporting documents, that would allow for these changes.
A copy of the permit application and IDEM’s preliminary findings are available at:
Topeka Public Library IDEM Northern Regional Office
122 N. Main Street 300 N. Michigan Street, Suite 450
Topeka, IN 46571 South Bend, IN 46601-1295
A copy of the preliminary findings is available on the Internet at: http://www.in.gov/ai/appfiles/idem-caats/.
How can you participate in this process?
The date that this notice is published in a newspaper marks the beginning of a 30-day public comment period. Ifthe 30th day of the comment period falls on a day when IDEM offices are closed for business, all comments must be postmarked or delivered in person on the next business day that IDEM is open.
You may request that IDEM hold a public hearing about this draft permit. If adverse comments concerning the air pollution impact of this draft permit are received, with a request for a public hearing, IDEM will decide whether or not to hold a public hearing. IDEM could also decide to hold a public meeting instead of, or in addition to, a public hearing.If a public hearing or meeting is held, IDEM will make a separate announcement of the date, time, and location of that hearing or meeting. At a hearing, you would have an opportunity to submit written comments and make verbal comments. At a meeting, you would have an opportunity to submit written comments, ask questions, and discuss any air pollution concerns with IDEM staff.
Comments and supporting documentation, or a request for a public hearing should be sent in writing to IDEM at the address below. If you comment via e-mail, please include your full U.S. mailing address so that you can be added to IDEM’s mailing list to receive notice of future action related to this permit. If you do not want to comment at this time, but would like to receive notice of future action related to this permit application, please contact IDEM at the address below. Please refer to permit number 087-30645-00007 in all correspondence.
Comments should be sent to:
Janet Mobley
IDEM, Office of Air Quality
100 North Senate Avenue
MC 61-53 IGCN 1003
Indianapolis, Indiana 46204-2251
(800) 451-6027, ask for extension (4-5373)
Or dial directly: (317) 234-5373
Fax: (317) 232-6749 attn: Janet Mobley
E-mail: jmobley@idem.in.gov
All comments will be considered by IDEM when we make a decision to issue or deny the permit. Comments that are most likely to affect final permit decisions are those based on the rules and laws governing this permitting process (326 IAC 2), air quality issues, and technical issues. IDEM does not have legal authority to regulate zoning, odor or noise. For such issues, please contact your local officials.
For additional information about air permits and how you can participate, please see IDEM’s Guide for Citizen Participation andPermit Guide on the Internet at: www.idem.in.gov.
What will happen after IDEM makes a decision?
Following the end of the public comment period, IDEM will issue a Notice of Decision stating whether the permit has been issued or denied. If the permit is issued, it may be different than the draft permit because of comments that were received during the public comment period. If comments are received during the public notice period, the final decision will include a document that summarizes the comments and IDEM’s response to those comments. If you have submitted comments or have asked to be added to the mailing list, you will receive a Notice of the Decision. The notice will provide details on how you may appeal IDEM’s decision, if you disagree with that decision. The final decision will also be available on the Internet at the address indicated above, at the local library indicated above, and the IDEM public file room on the 12th floor of the Indiana Government Center North, 100 N. Senate Avenue, Indianapolis, Indiana 46204-2251 and IDEM Northern Regional Office, 300 N. Michigan Street, Suite 450, South Bend, Indiana 46601-1295.
If you have any questions please contact Janet Mobley of my staff at the above address.
Iryn Calilung, Section Chief
Permits Branch
Office of Air Quality
Jm
LC 84 N22